Client
Alder Street Parish
Where
Hosford-Abernethy, Portland
Roof
Natural slate
Work
Natural slate restoration
Year
2025
The brief
Two contractors had quoted a full tear-off and new synthetic slate. The parish wanted to keep the roof the building was consecrated under, if it could be kept.
What we found
The slate itself was mostly sound. What had failed were the iron nails, rusted through after a century, and the valley metal, which let water into the trusses above the north aisle.
What we did
Stripped one slope at a time, sorting every slate on the lawn: sound, trimmable, or broken.
Relaid 70% of the original slate on new felt and copper nails, three inches of headlap on every course.
Matched the rest with unfading grey-black slate from the same Vermont district, mixed in so the new pieces disappear.
Re-lined both valleys and the bell gable with 20 oz copper, soldered in place.
How it ended
The roof looks as it did before, just tighter. The parish kept 4,700 square feet of its original slate out of the skip.
“We came close to losing the roof the chapel was built with. Now it should outlast all of us.”
Parish building committee

Relaid slate meeting the stone at the north transept

Original slate on the north slope before the relay
Weeks 1–4
North slope: strip, sort, relay
Weeks 5–10
South slope and transept
Weeks 11–14