Client
City library district
Where
St. Johns, Portland
Roof
Natural slate
Work
Slate and copper
Year
2024
The brief
The library’s box gutters, built into the cornice, had been patched with tar for decades. Water was running behind the stone and staining the reading room ceiling.
What we found
The slate was good. The box gutters were not: the original tin linings had been tarred over four or five times, and the wood under them had rotted along two sides.
What we did
Opened the cornice and replaced rotten gutter boards with new fir, shaped to the original profile.
Re-lined the box gutters in 20 oz copper with soldered flat-lock seams and expansion joints every 30 feet.
Relaid the lower three courses of slate over the new gutter edge, and repointed the hips.
Kept the library open throughout, working from scaffold towers with a covered entrance.
How it ended
Two winters since, the reading room ceiling is dry. The copper has gone bronze and will turn green along the cornice over the next twenty years.
“They found the problem nobody else had looked for, and fixed that instead of selling us a roof.”
Facilities manager, library district

Copper gutter linings formed on site

Hip slate after the first rain
Weeks 1–3
Scaffold, open the cornice
Weeks 4–9
Gutter boards and copper linings
Weeks 10–12